NO. |
PARTIES |
BRIEF DESCRIPTION OF PROJECT AND VALUE |
NATURE OF DISPUTE |
APPROX. AMOUNT IN DISPUTE |
RESULT |
|
1 |
(September 1992)
National Building Contractor and National Specialist
Mechanical and Electrical Subcontractor |
£2m Design and Build Mechanical &
Electrical Subcontract on £10m Design and Build Leisure
Centre Contract |
Numerous and complex claims and
counterclaims re delay and disruption. Also involving
“defects” disputes. |
Claim 1,200,000
Counterclaim 530,000
TOTAL £1,730,000
Plus complex “Defects” issues |
Fully resolved in a two day mediation. |
| 2
|
(December 1992)
Specialist
Electrical Control Systems Company and a Water Engineering Company
|
Model
Form A Subcontract Electrical Control Systems
|
Extensions
of time, acceleration costs, increased costs, loss and expense claims,
financing charges, counterclaim for liquidated damages, determination of
Sub-Subcontract.
|
Main
claim £100,000
Counterclaim
for liquidated damages
|
Settled
in the process of agreeing preliminary mediation arrangements with the
parties and just after preparation of the Summaries of Cases.
|
| 3
|
(March/April
1993)
Korean,
Chinese and German Developers, Government Officials, Building
Contractors and Consultants
|
Civil
Engineering infrastructure works, major hotel, office and apartment complex
in China. Contract value approximately £150 million
|
Multi-party
disputes involving disagreements concerning design, construction costs,
delays, loss of revenue, specification, quality of workmanship, etc.
|
£15
million
|
Appointed
to prepare independent expert’s report. Whilst in China agreed with the
parties to adopt mediation techniques and held a series of meetings, both
jointly and separately, with various parties for one week. All outstanding
disputes were resolved.
|
| 4
|
(June
1993)
Tripartite
Joint Venture Company involving Arabian, Turkish and Italian Interests
|
Desalination/power
generation plant located in the Middle East.
|
Disputes
between two of the three joint venture parties as to split of cost
liabilities for different parts of the construction works.
|
Approx
$(US) 2.1 million
|
Settled
after a two day mediation followed by Mediator’s adjudication on certain
points, as requested by the parties, followed by a further one day mediation
which achieved settlement
|
| 5
|
(1994)
International
Hostel Organisation
London Based
Building Contractor
|
New
Hostel Accommodation
|
Final
account dispute (involving several hundred disputed account items),
Contractor’s loss and expense/damages claims. Employer’s Counterclaims for
liquidated damages and defects
|
In
excess of £1m
|
Four
days of mediation followed by agreed exercises by QS’s of both parties,
followed by three further single day mediation meetings. Mediated settlement
reached.
|
| 6
|
(April
1996)
Civil
Engineering Contractor and Specialist Bridge Lifting Contractor
|
Repair
Works to Motorway Bridges
|
Claims
and Counterclaims re late info., slow progress, thefts, access problems, lack
of notices, variations, late approvals, construction errors.
|
£390,000
|
Fully
resolved in a one day mediation.
|
| 7
|
(April
1996)
Large
International Contractor (Power Transmission.
Electrical Installations) and Joint Venture Subcontractor for Electrical
Installations
|
Large
Bulk Handling Terminal
|
Claim
and counterclaim re variations, prolongation, premium time, lost
productivity, finance costs, contra charges, lack of possession, late design,
changed working methods, LAD’s, Scope of Work.
|
£1.5
million
|
Settled
in September 1996 after a one day mediation and four months further dialogue
with the parties.
|
| 8
|
(August
1996)
Tripartite
dispute. District Council, Building Contractor, Specialist Glazing Contractor
|
Squash
Courts in District Council Leisure Centre
|
Alleged
‘failure’ of glass walls to squash courts. Conflicting evidence and testing
by expert witnesses. Costs of testing, experts reports, loss of use,
financing costs, replacement costs, legal fees. Validity of ‘promises’ from
competitor specialists. Consideration of revised design solutions.
|
£122,000
|
After
a one day mediation the parties mutually agreed to withdraw from the
mediation, primarily because the expert witnesses were diametrically
opposed. It was felt by both main parties that a return to mediation might
be possible at a future date.
|
| 9
|
(September 1996)
Government
Agency, Worldwide
Procurement and Forwarding Company
|
Hospital
in Africa
|
Disputes
concerning qualiy of goods supplied and freight packing/storage provisions/
damage to switchgear
|
£77,000
|
Settled
in a one day mediation.
|
| 10
|
(March
1997)
Machine
Tool Company
Manufacturing
Company
|
Supply
of Machine tools £15,000.
|
Breach
of Contract, Repudiation, Loss of Profit.
|
£10,000
|
Settled
in a three hour mediation under the Central London County Court Mediation
Pilot Scheme.
|
| 11
|
(May
1997)
Tripartite
dispute. University, Building Contractor, Architect (P.1. Insurers)
|
University
Student Accommodation £15 million
|
Contractor’s
claim for loss and expense arising from the late issue of information.
University’s Counterclaim for LAD’s for late completion by the Contractor.
University’s claims against Architect for liability for Contractor’s loss and
expense as a result of late issue of information by the Architect. Architect’s
claim against University for additional fees. University’s claims against
Architect for lost income and costs incurred in providing alternative
accommodation for students.
|
£5.4
million.
|
Settled
between University and Contractor after two days of mediation with a seven
day gap. Dispute between University and Architect still to be resolved.
|
| 12
|
(July
1997)
Property
Company
Building
Firm
|
Construction
of Lift Shaft
£16,000.
|
Disputes
concerning rates for variations and extra works and work not in accordance
with specification.
|
£6,000
|
Settled
in a three hour arbitration under the Central London County Court Mediation
Pilot Scheme
|
| 13
|
(July
1997)
Housing
Tenant
Housing
Trust
|
Landlord
and Tenant Dispute
|
Dispute
concerning the pruning of trees, damage to garden lawn and shrubs by
workmen. Repairs of fence.
|
Written
undertakings required re maintenance of trees. Supply of replacement
shrubs. Replacement of fence with a wall.
|
Settled
in 4 hour mediation under the Independent Housing Ombudsman’s Scheme with
CEDR as agent.
|
| 14
|
(February
1998)
Housing
Tenant
Housing
Trust
|
Landlord
and tenant dispute.
|
Dispute
concerning damp proofing work, compensation for discomfort, rent relief,
electrical costs.
|
£700
|
Settled
in 4 hour mediation under the Independent Housing Ombudsman’s Scheme with
CEDR as agent.
|
| 15
|
(February
1998)
Government
Agency
Consulting
M&E Engineers
(P
I Insurers)
|
Design
and supervision of mechanical and electrical installations on office building
project.
|
Dispute
concerning professional negligence action under Contract and under warranty
to the eventual building owner.
|
£1.1
million including legal costs. Counterclaim including legal costs in excess
of £300,000.
|
The
mediation was convened only 2 weeks before the commencement of the trial.
Both parties made concessions but the matter still proceeded to trial.
Mediation was used too late in the dispute.
|
| 16
|
(February
1998)
Building
Employer (Commercial Company).
Project Managers
Consultant
Architects
Quantity
Surveyors
M&E
Engineers
Structural
Engineers
Management
Contractor
Works
Contractors
|
New
lecture theatre complex.
|
Any
disputes connected with the project.
|
|
Appointed
in advance of construction to act as mediator as and when any disputes arise
throughout the design, construction and maintenance periods.
|
| 17
|
(March
1998)
Exhibition
Contractor
Exhibition
Display Company.
|
Stands
for National Exhibitions at the NEC.
|
Claims
and counterclaims concerning underpayments, quality of work, late completion,
variations, work by other contractors, remoteness of damages paid to third
party, interest charges, legal costs.
|
Claim
£38,000. Counterclaim for £25,000 (including legal costs).
|
Settled
in a one day mediation.
|
| 18
|
(May
1998)
Building
Contractor
House
Owner
|
House
extension/Granny Flat £54,000.
|
Claims
and counterclaims concerning underpayments for work carried out, variations,
omissions, work by others, defective and incomplete work, diminution in
value, misrepresentation compensation costs, interest charges, legal and
experts' costs.
|
Claim £15,000
Counterclaim £34,000
Costs £50,000
______
£99,000
______
|
Settled
in a one day mediation (Commenced 10.00 a.m. settled 1.00 a.m. next morning).
|
| 19
|
(May
1998)
Machine
Metalwork Company
Machine
Manufacturer
|
Supply
of drilling machine.
|
Claim
and counterclaim concerning drilling machine performance specification, loss
of profit, damages, interest, legal costs
|
£275,000.
|
Settled
in a one day mediation.
|
| 20
|
(June
1998)
House
Owner
Joinery
Manufacturer, Architect
|
Design
and supply of doors and windows.
|
Design
and dimensions of french doors and georgian windows.
|
£3,600
and ownership of joinery.
|
Settled
in a 5 hour mediation.
|
| 21
|
(October
1998)
House
Owner
Architect
Structural
Engineer
Building
Contractor
|
Extension
to an existing cottage resulting in its demolition and complete redevelopment
and replacement by a substantial residence.
|
Claims
and counterclaims concerning architectural and structural design and supervision,
workmanship defects. Involving basement structural and tanking work, land
drains, electrical work, windows, brickwork quality, sewerage and decorative
work. Including claims for delay, financing costs, professional fees,
discomfort and stress and legal and expert witness costs.
|
In
excess of £200,000 including legal costs.
|
Settled
after two days of mediation with a further half day mediation in respect of
legal costs.
|
| 22
|
(December
1998)
Charity
Advice Centre
Architect
|
Refurbishment
and alterations to city centre premises.
|
Quantum
of Architects fees when budget cost (£80,000) on which fees were tendered
increased by almost 100%.
|
£3,500
|
Settled
in a 2 hour conciliation under the RIBA conciliation service.
|
| 23
|
(April
1999)
Residential
Property Owner
Architect
|
Extension
and alterations to private dwelling
|
Liability
for Architect's fees.
|
£750
|
Settled
in a 2 hour conciliation under the RIBA conciliation service.
|
| 24
|
(November
1999)
Residential
Property Owner
Architect
|
Design
of extension and alterations to private dwelling.
|
Liability
for Architect's fees.
|
£3,000.
|
Settled
in a 3 hour conciliation under the RIBA conciliation service.
|
| 25
|
(March
2000)
Concrete
and Formwork Subcontractor, Building Contractor
|
Office
Development
|
Variations,
Claims and Counterclaims for delays and loss and expense, LAD’s, interest,
costs.
|
Claim £410,000
Counterclaim £484,000
|
Two
day mediation. Settled by the parties after mediation.
|
| 26
|
(May
2000)
Residential
Property Owner
Building
Contractor
|
Works
to Grade II Listed Manor House.
|
Repudiation,
abatement, value of work to Grade II listed Manor House. Defective Work,
Interest, Costs.
|
Claim £64,000
Counterclaim £22,000
|
Settled
in a one day mediation subject to provision of financial status information
by builder.
|
|
27
|
(October
2000)
Main
Contractor
Fencing
Contractor
|
Metal
Fencing to Housing Development
|
Measurement
and Valuation disputes on F/AC. Disputes as to method of measurement.
|
£92,000
|
Settled
in a one day mediation. Settlement included an agreement to re-establish a
working relationship and future work.
|
| 28
|
(November
2000)
Painting
& Decorating Subcontractor,
Main
Contractor
|
Four
varied contracts.
|
Valuation
of Final Accounts. Disputes as to valid records and documentation,
observance of conditions of contract.
|
Claim £280
Counterclaim £10,000
Costs £71,000
|
Settled
in a one day mediation. The litigation costs were the major factor in the
mediation.
|
| 29
|
(January
2001)
House
owner, Architect, Contractor
|
Refurbishment
of holiday home.
|
Incomplete
and unsatisfactory work, Payments, Delays, Damp, Design of Windows.
|
Counterclaim,
Claim, Costs £200K
|
House
owner & Architect settled. House owner and builder did not settle.
|
| 30
|
(March
2001)
Drainage
Subcontractor, Main Contractor
|
Drainage
to police station.
|
Final
account values of measured work, dayworks,
Counterclaims,
Interest, Costs.
|
Claim £50,000
Counterclaim £12,500
|
Settled
in a one day mediation.
|
| 31
|
(March
2002)
Landlord,
Letting Agent
|
Property
Management
|
Non
payment of rent by tenant, damage, deposit.
|
£1,215
|
Mediation
attempted by telephone. Parties decided to proceed to small claims court. No
fees charged.
|
| 32
|
(May
2002)
House
Owner, Builder
|
Extension
to house.
|
Value
of work, defective work, cost of completing using another builder.
|
£12,500.
|
Settled
in a one day mediation. Court proceedings stayed.
|
|
33
|
(June 2002)
Building Contractor, Factoring Company
|
Mechanical services to offices
|
Factor’s claim for unpaid invoices re insolvent subcontractor.
Set off for incomplete and defective work, extra costs of completion.
Legal costs.
|
£24,000.
|
Settled in a one day mediation. Court proceedings stayed.
|
|
34
|
(Aug 2002)
Building Contractor, Partition and Plastering Subcontractor
|
Commercial Development
|
Final Account and loss and expense claims.
|
£200,000
|
One day mediation. Parties reached a settlement one month
later.
|
|
35
|
(Oct 2002)
Main Contractor, Dry Lining/Partition Subcontract
|
Museum.
|
Final Account, contra charges, LADS
|
£30,000.
|
Settled in a half day mediation.
|
|
36
|
(Feb 2003)
Main Contractor, Curtain Walling & Window Subcontractor
|
Commercial, Retail and Residential Development
|
Final Account, Claims, Liquidated and Ascertained Damages,
Damages, Extensions of Time
|
Claim £750,000
Counterclaim £950,000
|
Settled after a one day mediation and six months of
negotiations.
|
|
37
|
(May 2003)
Building Contractor, Property Company
|
Commercial Development
|
Valuation of Variations, Claims re delay and disruption.
|
Claim £600,000
Counterclaim £225,000
|
Settled in two days of mediation and interim telephone calls.
|
|
38
|
(June 2003)
House Buyer, House Builder
|
Detached House
|
Defective work, compensation, legal costs, retention money.
|
£16,500
|
Settled in a four hour mediation.
|
|
39
|
(July 2003)
Factory Tenant, Developer, Building Contractor
|
Factory
|
Defective work, Consultant’s costs, legal costs, remedial
scheme.
|
Tenant: £687,000
Developer: £405,0000
|
Settled in a one day mediation and subsequent telephone calls.
|
|
40
|
(August 2003)
Science Park, Construction Company
|
Science
Park
Building
|
Defective work, set-off claim, consultant’s costs, loss of
rent, Final Account Agreement
|
£40,000
|
Settled in a one day mediation.
|
|
41
|
(October 2003)
House Buyer, Planning Consultant
|
Extension to maisonette.
|
Losses incurred due to incorrect planning permission advice.
|
£16,500.
|
Settled in a 2½ hour mediation.
|
|
42
|
(November 2003)
Steelwork Subcontractor, Main Contractor
|
Court Building
|
Final Account Value including variations and claims and general
damages, claim for loss of contribution.
|
£360,000
|
Settled in a one day mediation.
|
|
43
|
(November 2003)
Groundwork Subcontractor, Building Contractor
|
Research Laboratories
|
The terms and conditions of contract were in dispute.
There had been two adjudications and litigation had commenced.
Final Account including remeasure, variations, Dayworks, loss
and expense, disruption, interest, overheads, increased costs, ground
conditions.
|
£3 million.
|
Settled in a two day mediation.
|
|
44
|
(December 2003)
Conservatory Company, Houseowner
|
Conservatory
|
Payment due, defective work, damage to property, damages,
interest, legal costs
|
£28,000
|
Settled in a one day mediation.
|
|
45
|
(December 2003)
M&E Subcontractor, ME& Contractor
|
Multiple retail outlet.
|
Valuation of variations, non payment.
|
£70,000
|
Settled prior to mediation meeting.
|
|
46
|
(December 2003)
Bricklaying Trade Contractor, Construction Company
|
Residential apartments.
|
Final Account, Variations, extensions of time, loss and
expense, LAD’s Counterclaims
|
Claim £490,000
Counterclaim £260,000
________
£750,000
|
Settled at a one day mediation and subsequent telephone
negotiations via the mediator.
|
|
47
|
(March 2004)
Clay Extraction Company, Holding Tank Supplier, GRP Tank
Manufacturer
|
Clay slurry holding. Tanks for Pottery Industry.
|
Damages arising from collapse of tank. Cost of
replacement tank and associated equipment. Clean-up costs. Damage to
property. Remedial work to other tanks, professional fees, legal costs.
|
£60,000.
|
Settled in a one day mediation.
|
|
48
|
(May 2004 )
Architectural Design Company, Staircase Manufacturer
|
Feature steel staircases on university and house.
|
Unpaid invoices. Counterclaims for determination,
repudiation, extra completions costs, loss of profit.
|
£49,000.
|
Settled in a one day mediation.
|
|
49
|
(May 2004)
Leased Building Owner, Property Development Company, Penthouse
Purchaser.
|
Lease and development of property.
|
Tri-partite dispute. Property Lease and Development Costs.
Forfeiture of lease. Injunction to restrain sale of lease, assignment of
lease. Unpaid commission and share of profit, conspiracy.
|
Approx £2 million.
|
Dispute narrowed but not settled.
|
|
50
|
(August 2004)
Steelwork Fabricator, Coating Subcontractor
|
Coating and bridge steelwork
|
Final account value, delays, contra charges, future trading
|
£6,000
|
Settled in a half day mediation.
|
|
51
|
(September 2004)
Masonry Company, Wire Products Company, Metalwork Company
|
Construction of 3 factory and office units.
|
Final Account Value, Counterclaims, Interest, Working
relationships.
|
£64,000.
|
The parties narrowed their differences from £64,000 to £5,000
but did not settled on the day. A settlement was reached 3 weeks
later on the basis agreed at the mediation.
|
|
52
|
(December 2004)
Property Developer, Building Contractor
|
Construction of 2 residential properties
|
Final Account Value, delays, defective work, liquidated damages
|
£118,000
|
Settled in a one day mediation.
|
|
53
|
(February 2005)
Commercial Lorry Fleet Company, Road Hauliers
|
Hire of commercial lorries
|
Disputed invoices for hire, repairs, replacements, road fund
rebate, etc.
|
£70,000.
|
Settled in a one day mediation.
|
|
54
|
(February 2005)
Metropolitan Council, Civil Engineering Contractor
|
Refurbishment of pier structure
|
Cost of remedial works, compensation events, damages, loss of
income
|
£3.5 m
|
Settled in a one day mediation.
|
|
55
|
(April 2005)
Construction Company,
Timber Building Subcontractor
|
Timber buildings at holiday centre.
|
Final Account value, delays, loss and expense, LAD’s,
Counterclaims, interest, costs.
|
£1 million
|
Settled at a one day mediation and telephone calls via the
mediator and parties in the following 5 days.
|
|
56
|
(May 2005)
Supplier of Galvanised Steel, Roller Shutter Manufacturer
|
Supply of galvanised steel.
|
Quality of materials supplied, fitness for purpose,
counterclaim for losses.
|
£45,000
|
Settled in a one day mediation.
|
|
57
|
(July 05)
House Owner, Building Company
|
Erection of porch and conservatory and supply and installation
of replacement windows.
|
Claim for non-payment. Counterclaim for defects in
construction including inadequate foundations and other damages.
|
£20,000
|
Settled in a one day mediation.
|
|
58
|
(July 05)
Civil Engineering Contractor, Racing Stables
|
Construction of gallop.
|
Value or work carried out. Livery fees, sale of horse.
|
£80,000.
|
Settled in a ½ day mediation and via subsequent telephone calls
and a meeting of the parties.
|
|
59
|
(August 05)
Building Contractor, Housing Development Company
|
Construction of 80 apartments.
|
Extensions of time, LAD’s, valuation of variations, loss and
expense.
|
£4 million.
|
Settled at two concurrent days of mediation.
|
|
60
|
(August 05)
Aviation Company, Private Buyers
|
Sale
of Vulcan Bomber
|
Condition of aircraft, storage costs/damages, identity of
contracted parties, fitness for purpose.
|
£60,000
|
Settled at a one day mediation.
|
|
61
|
(September 05)
Civil Engineering Company, Petrol Service Station Company
|
Installation of underground tanks and equipment at service
station.
|
Ground conditions, delay costs, variations, legal costs.
|
£26,000.
|
Settled at a one day mediation.
|
|
62
|
(September 05)
Groundworks Subcontractor, Building Contractor
|
Groundworks and drainage to car showrooms
|
Final Account Value, Contra charges, interest, legal costs.
|
£75,000
|
Settled at a one day mediation.
|
|
63
|
(October 05)
Adjacent Property Owners (2 married couples)
|
Neighbour dispute.
|
Rights of way, access for inspection and maintenance, adverse
possession of land claim, loss of light from tall growing trees,
allegation of rude, threatening and violent behaviour. Future
relationships.
|
Not applicable.
|
Settled at a one day mediation.
|
|
64
|
(November 05)
Steelwork Contractor, Developer
|
Supply and erection of steel staircases on four contracts.
|
Value of work carried out, counterclaim for defective work and
damages, interest, legal costs.
|
£37,000
|
Settled after a one day mediation and subsequent telephone
negotiations via the mediator.
|
|
65
|
(February 06)
Commercial Estate Agency, Seller of Care Home
|
Sale
of property
|
Entitlement to introduction/selling fee
|
£40,000.
|
Settled prior to the mediation meeting.
|
|
66
|
(March 06)
Steel Fabricator and Erector, Cold Store Construction Company
|
Steel frame to cold store.
|
Final Account value including value of variations, acceleration
claims, premium time working, delay costs, counterclaims.
|
£8,000
|
Settled at a one day mediation.
|
|
67
|
(July 06)
Building Contractor, Houseowners
|
Fire damage reinstatement and extension to and refurbishment of
residence
|
Final Account Value, loss and expense, disruption, costs to
complete, interest, temporary accommodation, distress and inconvenience,
legal costs.
|
£900,000.
|
Settled at a one day mediation.
|
|
68
|
(July 06)
Subcontractor, Civil Engineering Contractor
|
Arts Centre
|
Final account value, contra charges, interest costs.
|
£7,500.
|
Settled at a one day mediation.
|
|
69
|
(Sept 06)
Metal Castings Company, Fuel Conservation Services Company
|
Supply of heat resistant alloy castings.
|
Defective goods, value of goods supplied, scrap value,
counterclaim costs.
|
£9,000.
|
Settled at a half day mediation.
|
|
70
|
(Nov 06)
Parochial Church Council, Building Company
|
Work to Church Tower.
|
Quality of work, remedial costs, legal costs.
|
£30,000.
|
Settled at a half day mediation.
|
|
71
|
(February 07)
Manufacturer, Wire Supplier
|
Supply of cut and coiled steel wire for the manufacture of
supermarket baskets and trolleys.
|
Breach of fixed price agreement, failure to supply on time,
late payment, repudiation, duress, failure to mitigate losses,
incorporation of terms, damages.
|
£1,260,000 plus costs. Counterclaim £90,000 plus costs.
|
Settled at a one day mediation.
|
|
72
|
(March 07)
Neighbours
|
Neighbour Dispute
|
Replacement of a party fence, height and design of fence.
Abusive behaviour, relationship as neighbours and relationships at work.
|
£800. The dispute also involved the relationship between
the parties.
|
Settled at a half day mediation.
|
|
73
|
(April 07)
Bathroom Specialist, House Owner
|
Plumbing work and fitting out new bathroom.
|
Defective work, counterclaim costs, legal costs.
|
£8,000.
|
Settled at a half day mediation.
|
|
74
|
(May 07)
Blasting and painting Contractor, Bridge Steelwork Contractor.
|
Bridge steelwork.
|
Defective work. Value of extra work. Allegations of criminal
misrepresentation.
|
£220,000
|
Settled at a one day mediation.
|
|
75
|
(July 07)
Architect, Houseowners, Owners Agent
|
Design of New House
|
Payment for architectural services, breach of copyright.
|
£1,300
|
Settled by mediation via telephone and post.
|
|
76
|
(August 07)
Recruitment Company, Leisure Services Company
|
Recruitment company premises.
|
Damage to property by adjacent building works. Temporary
relocation costs. Business interruption costs.
|
£700,000.
|
The parties narrowed the amount in dispute to £250,000 but no
settlement was achieved on the day. (Ongoing?)
|
|
77
|
(September 07)
Watch Owner, Prestigious International Watch Company
|
Replacement of diamond encrusted watch dial.
|
Watch dial with high sentimental value lost (but re-found as a
result of mediation).
|
£2,500
|
Settled by mediation by telephone, e-mail and post.
|
|
78
|
(October 07)
Construction Company, Land Survey Firm
|
Levels survey of construction site.
|
Survey errors, additional rock break costs, delay costs.
Interest, legal costs.
|
£180,000.
|
Settled at a one day mediation.
|
|
79
|
(December 07)
Pentecostal Church, Petroleum Corporation, Petrol Filling
Station Company
|
Church, Community Centre and Nursery.
|
Contamination from petrol filling station.
|
£540,000.
|
Settled at a one day mediation.
|